Q.
A certain number of people can complete a piece of work in 12 days working 5h a day. If the number of men is decreased by half, then how many hours a day should they work, so that the work is to be completed in 15 days?
59
137
Time and Work, Pipes and Cisterns
Report Error
Solution:
(i) Use variation method.
(ii) Consider the number of men as x in first case. Therefore, the number of men in second case is x/2.
(iii) Use W1M1D1H1=W2M2D2H2 and find H2.